Safe Work Method Statement Example: A Filled-In SWMS Explained


Last reviewed: November 2026
The short answer: a good safe work method statement (SWMS) names the high risk construction work, breaks the job into steps, lists the hazards at each step, sets out the controls and says who puts them in place and how they're checked. Below is a filled-in SWMS extract for repainting the outside of a two-storey house from a mobile scaffold as part of a renovation, with each section explained. It's an illustration, not a ready-to-use SWMS: yours needs to reflect your site, equipment and crew.
If you'd rather start from a pre-filled version for your trade, browse our SWMS templates.
What goes in a SWMS?
Under the model WHS Regulations, a SWMS for high risk construction work must:
Identify the work that is high risk construction work
Specify the hazards and the risks to health and safety
Describe the measures that will control the risks
Describe how those control measures will be put in place, monitored and reviewed
Regulators also expect it to include your business details, and to be written so the people doing the work can understand and follow it. A short, clear SWMS is better than a long one nobody reads.

The example job
Job: Repaint the external walls of a two-storey house as part of a renovation and refurbishment of the home. Method: Two painters working from a mobile aluminium scaffold, using brushes and rollers. Why a SWMS is legally required: renovation and refurbishment is construction work, and this job involves a risk of a person falling more than 2 metres, which is one of the high risk construction work categories. There are also overhead powerlines near the front of the house, which adds a second category. Not every repaint is construction work: testing, maintenance and repair work of a minor nature is excluded from the definition, so check the scope of your job.
South Australia: SA lowered its fall threshold for high risk construction work from more than 3 metres to more than 2 metres on 1 July 2026, in line with the other WHS states and territories.
Section 1: Business and job details
Field | Example |
|---|---|
Business name and ABN | Coastline Painting Pty Ltd, ABN 00 000 000 000 |
Contact | Sam Taylor, 0400 000 000 |
Job and address | External repaint, 12 Example Street, Suburb |
Principal contractor (if any) | None. The renovation is below the construction project threshold for this state, so there is no principal contractor |
Prepared by | Sam Taylor, Director |
Date prepared | 3 November 2026 |
Review date | Before each new job, or if the method or controls change |
Why it matters: it shows the SWMS belongs to this business and this job. On a construction project with a principal contractor, you need to give them a copy before the high risk work starts.
Section 2: High risk construction work involved
Work that involves a risk of a person falling more than 2 metres
Work carried out on or near energised electrical installations or services (overhead powerlines at the front of the house)
Why it matters: this is the first thing an inspector or principal contractor checks. If the job involves more than one type of high risk construction work, list them all, as this example does.
Section 3: Task steps, hazards and controls
Step | Hazards and risks | Controls | Who |
|---|---|---|---|
| Members of the public walking under the work area. Overhead powerlines near the front of the house. Uneven ground. | Identify powerlines before setting up. Keep the scaffold, workers and tools outside the exclusion distances that apply, and contact the electricity network operator about the requirements for this site. Set up barriers and signs around the work area. Check the ground is firm and level, and use base plates where needed. | Sam |
| Falls during erection. Scaffold collapse. Manual handling strain. | Erected by a competent person following the manufacturer's instructions. A scaffolding licence is required to erect, alter or dismantle scaffolding where a person or object could fall more than 4 metres. Fit the bracing, stabilisers or outriggers the manufacturer specifies and don't exceed the load limits. Use the manufacturer's safe erection method so workers are protected before guardrails are complete. Two people to lift and fit components. Guardrails, mid-rails and toeboards on the working platform. Castors locked. | Sam and Jo |
| Missing or damaged parts leading to collapse or falls. | Inspect before first use each day and after any change or bad weather. Tag the scaffold as safe to use. Don't use it if anything is missing or damaged. | Sam |
| Falls from height. Overreaching. Dropped tools hitting people below. Paint splashes to the eyes. | Use the scaffold's internal access ladder or stairs. Never climb the outside of the scaffold. Work only from inside the guardrails, and never climb on guardrails or use ladders on the platform. Keep tools and paint tins away from the platform edge. Keep the exclusion zone in place below. Safety glasses when painting overhead. | Sam and Jo |
| Scaffold tipping. Falls. Striking powerlines. | Nobody on the scaffold while it's moved. Clear the path of obstacles. Check the new position stays outside powerline exclusion distances. Lock castors before climbing back on. | Sam and Jo |
| Falls during dismantling. Manual handling strain. Spills. | Dismantle in reverse order to the manufacturer's instructions, keeping workers protected until the last level comes down. Two-person lifts. Clean brushes and dispose of waste water as the product label directs. | Sam and Jo |
Why it matters: this is the heart of the SWMS. A few things to notice:
The steps follow the job in order. Setting up and packing down are where many incidents happen, so they're included.
The hazards are specific. "Falls" is vague. "Falls during erection" and "overreaching from the platform" tell the worker what to watch for.
The controls start with the most effective. Guardrails come before signage and PPE, following the hierarchy of controls.
Every control has a name next to it. If nobody owns a control, it tends not to happen.
Section 4: How controls are monitored and reviewed
Question | Example answer |
|---|---|
How will we check controls are in place? | Sam inspects the scaffold before first use each day and checks the exclusion zone at the start of each day. |
What happens if a control isn't working? | Work stops until it's fixed. Any worker can stop the job if they think it's unsafe. |
When will this SWMS be reviewed? | Before each new job, if the work method changes, if a control is changed, after any incident or near miss, or if a worker raises a concern. |
Why it matters: this is the part most often left out, and it's one of the four things the law requires. It shows the SWMS is a working document, not just paperwork.
Section 5: Sign-on
Name | Signature | Date |
|---|---|---|
Sam Taylor | 3/11/2026 | |
Jo Nguyen | 3/11/2026 |
Why it matters: workers must be given the information and instruction they need to understand the SWMS before they start. A sign-on sheet is the simplest evidence that you've done that. Go through the SWMS with the crew, ask for their input and fix anything that doesn't match how the work is done. Consulting your workers is a legal duty, and it's what makes the SWMS accurate.
How long do you keep a SWMS?
Keep the SWMS available at the workplace while the work is under way, so workers can check it. Keep it until the high risk construction work is finished. If a notifiable incident happens in connection with the work, keep it for at least two years from the date of the incident.
Common mistakes in SWMS
Not matching the job. A SWMS for a single-storey house used on a three-storey commercial building will miss hazards. Check it against the site before each job.
Missing the high risk construction work. If the SWMS doesn't say which category applies, it doesn't meet the basic requirement.
Controls that rely only on PPE or "be careful". Look for higher-level controls first.
No one named against controls. Add a name or role to each.
Never reviewed. Update the SWMS when the method, site or controls change.
Not signed. Without a sign-on, it's hard to show workers were told about it.
Do you need a SWMS if you're not doing construction work?
Not legally. A SWMS is only required for high risk construction work. But plenty of businesses outside construction use the SWMS format for any task with significant hazards, such as cleaning at height, warehouse loading or working alone. It's the same thinking as a JSA: break the job into steps, find the hazards and set the controls. Many clients and prequalification platforms also ask for "a SWMS" whatever the work is. For more on how SWMS, JSAs and risk assessments compare, read SWMS vs JSA vs risk assessment.
Get a SWMS for your work
Writing a SWMS from a blank page takes time. Our SWMS templates come with the task steps, hazards and controls already written for each job, aligned to Australian legislation and fully editable in Word. Add your business details, adjust them to your site and go through them with your crew.
Prefer to start from scratch? Download our free blank SWMS template.
SWMS example: common questions
Is there a standard SWMS template I have to use?
No. The regulations set out what a SWMS must contain, not the layout. Use any format that covers the four requirements and is easy for your workers to follow.
Can one SWMS cover several tasks?
Yes, as long as it deals with the hazards and controls for each high risk construction work activity. Keep it short enough that workers will read it, and split unrelated activities into separate SWMS.
Who writes the SWMS?
The business carrying out the high risk construction work prepares it, in consultation with the workers who'll do the job. On a construction project, give the principal contractor a copy before the work starts.
How detailed should a SWMS be?
Detailed enough that a worker reading it knows the hazards and what to do about them. Regulators warn that long, overly detailed SWMS are hard to understand and follow.
Does a SWMS need to be site-specific?
It needs to reflect the work and the conditions at the workplace. Review it before each new job and update it for anything different about the site.
What does SWMS stand for?
Safe work method statement. For the full guide, read What is a SWMS and do you need one?
Sources and further reading
Check your state or territory regulator for the current requirements that apply to you.
Everything OHS has been helping Australian businesses with WHS documents since 2008, and 15,000+ Australian businesses use our documents. This article is general guidance, not legal advice. Victoria has its own high risk construction work list under the Occupational Health and Safety Regulations 2017, so check the requirements for your state or territory.